From Inquiry to Executable Quotation: What the Factory Technical Review Needs

Clear application, geometry, standard, quantity and delivery information produces a specification and price that can be compared against the real project.

“Quote your lowest geomembrane price” does not define a comparable supply. A technical review first identifies the application, failure consequences, material function and acceptance basis, then confirms quantity, packing and schedule.

Project action list

What the procurement or project team should do next

  • Send drawings and representative site photographs

  • Attach the technical schedule or specification

  • State the quantity basis and permitted variation

  • Provide destination, Incoterm and required delivery date

Material samples reviewed against an inquiry specification
01

Technical conditions define the product

Provide application, subgrade, slope, contained liquid or loading, design life, cover system and governing documents. Drawings and written clauses are preferable to verbal summaries.

02

Define how quantities were calculated

Net area, purchase area and roll quantity are different. State whether overlaps, anchors, trimming, contingency and whole-roll rounding are included.

03

Delivery conditions affect landed cost

Destination, Incoterm, container type, unloading limits and required arrival date affect packing, booking and production planning.