International Procurement
Common risks and controls
- Unprotected steel rope against the membraneDirect contact can cut roll edges and conceal damage beneath the outer layers.
- Unknown roll massThe receiving team needs the gross roll mass to select adequately rated lifting equipment.
- Unloading order overlookedCheck access to each roll and avoid trapping the first-needed materials beneath later-use products.
International Procurement
Implementation steps
- Prepare the loading plan
Check roll dimensions, gross masses, container limits and the delivery sequence.
- Inspect the empty container
Check for leaks, contamination, protruding nails and floor damage.
- Secure and photograph
Document roll positions, supports, restraints, labels and the container seal.
- Coordinate unloading
Provide individual roll masses and the approved lifting and unloading arrangements before arrival.
International Procurement
Procurement and acceptance checklist
| Risk | Loading control | Receiving inspection |
|---|---|---|
| Core deformation | Use approved supports and stacking limits | Check core openings and roll ends |
| Membrane-edge damage | Protect ends and prevent contact with sharp or hard surfaces | Inspect edges for cuts and severe creases |
| Lost identification | Protect roll labels and retain a roll-number packing list | Match physical rolls to the documents |
| Moisture and contamination | Check container condition and keep packaging clean and dry | Inspect packaging, labels and accompanying geotextiles |
International Procurement
Project assessment
A geomembrane roll can arrive damaged even when the membrane itself tolerates normal moisture exposure. Wet packaging, illegible labels, deformed cores and inadequate restraint can affect identification and safe unloading. Plan loading using the roll dimensions and gross mass, container payload and floor limits, approved supports and stacking arrangements. Protect membrane edges from sharp metal and door frames. Send the receiving team the roll list, lifting requirements and unloading sequence before shipment, and use the manufacturer-approved lifting arrangement with correctly rated equipment.